Declared emergency actions in the solid waste landfill Abanilla (13/04/2016)

The Governing Council has been informed of the decision to declare the emergency of the actions that must be carried out in the municipal solid waste landfill in the area of ​​La Solana in the Sierra de Abanilla.

Thus, the Minister of Water, Agriculture and Environment has adopted the Order of February 10, 2016 by the still existing persistent risk of danger, it requires to continue to ensure the management of leachate and removal to authorized agent, and vessel sealing weir.

Given the size of the works has been necessary to include among the actions the review and adaptation of the technical project under which shall carry out the work of sealing and revegetation.

As for leachates, managing 8,500 toneladasdurante six months, with internal transfer of up to 75 tons per day and removed from the raft authorized manager, with an estimated 435,600 euros cost, which will be implemented by the company Zero Waste is planned .

The wording of sealing technical project, which has already been presented, as well as construction management and health and safety has a cost of 27,225 euros and is awarded to the company Getnisa.

Finally, regarding the execution of the works, which have been entrusted to Tragsa once received technical sealing project drafted by Getnisa, it has been issued the Order of April 7, 2016, complementary, which has also been reported at this meeting the regional government.

This order has been necessary because of the results of data collection for the technical project, which includes a much more serious situation than initially foreseen regarding leachate generation.

This has required spending adapt the execution of emergency works, an increase of 685,863 euros on estimated in February.

Thus, finally the budget of the project amounts to 2,036,836 euros, instead of 1,351,000 euros.

It also extends the time needed for implementation, according to the project schedule would be eight months, two more than originally estimated time months.

In parallel with the actions being undertaken to eliminate the risks on the environment and people, they are driving economic records to cover the costs of the subsidiary execution, which include the emergency, under the trade Proambiente.

Source: CARM

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información